Air Quality Monitoring

Phase 2 Year 3 dredging operations began on April 29, 2013.  Monitoring is conducted daily for river operations and at the Processing Facility during the dredging season.  View air quality monitoring on the Quality of Life Monitoring Interactive Map.  For Phase 2 air quality data, click on the calendar below.  Phase 1 data is available by clicking on the link at the bottom of the page.

Calendar (Please click on data for more information)

View Most Recent Data
«    June 2012    »
SundayMondayTuesdayWednesdayThursdayFridaySaturday
1
Processing Facility: Typical
River Operations: Typical
2
Processing Facility: Typical
River Operations: Typical
3
Processing Facility: Typical
River Operations: Typical
4
Processing Facility: Typical
River Operations: Typical
5
Processing Facility: Typical
River Operations: Typical
6
Processing Facility: Exceedance River Location E: Exceedance River Locations - All Other: Typical
7
Processing Facility: Exceedance River Operations: Typical
8
Processing Facility: Control River Operations: Typical
9
Processing Facility: Typical
River Operations: Typical
10
Processing Facility: Typical
River Location E: Control River Locations - All Other: Typical
11
Processing Facility: Exceedance River Location E: Control River Locations - All Other: Typical
12
Processing Facility: Typical
River Location E: Exceedance River Locations - All Other: Typical
13
Processing Facility: Exceedance River Operations: Typical
14
Processing Facility: Exceedance River Location E: Control River Locations - All Other: Typical
15
Processing Facility: Control River Location E: Exceedance River Locations - All Other: Typical
16
Processing Facility: Exceedance River Location E: Exceedance River Locations - All Other: Typical
17
Processing Facility: Exceedance River Operations: Typical
18
Processing Facility: Exceedance River Location E: Exceedance River Locations - All Other: Typical
19
Processing Facility: Typical
River Location D: Control River Location E: Exceedance River Locations - All Other: Typical
20
Processing Facility: Exceedance River Location D: Exceedance River Location E: Exceedance River Location F: Control River Locations - All Other: Typical
21
Processing Facility: Exceedance River Location D: Exceedance River Location E: Exceedance River Locations - All Other: Typical
22
Processing Facility: Typical
River Location D: Control River Locations - All Other: Typical
23
Processing Facility: Typical
River Operations: Typical
24
Processing Facility: Typical
River Operations: Typical
25
Processing Facility: Exceedance River Operations: Typical
26
Processing Facility: Typical
River Location D: Exceedance River Locations - All Other: Typical
27
Processing Facility: Typical
River Location D: Exceedance River Location E: Exceedance River Locations - All Other: Typical
28
Processing Facility: Control River Location D: Exceedance River Location E: Exceedance River Locations - All Other: Typical
29
Processing Facility: Exceedance River Location E: Control River Locations - All Other: Typical
30
Processing Facility: Typical
River Operations: Typical

Legend:

Typical Operations: Daily total PCBs under the standard.

Exceedance Level: Daily total PCBs exceed standard.

PollutantPerformance StandardMonitoring Frequency
PCBs (Residential Areas) 0.11 micrograms per cubic meter Continuous Monitoring
Daily (24-hour) basis
PCBs (Commercial/Industrial Areas) 0.26 micrograms per cubic meter Continuous Monitoring
Daily (24-hour) basis

Goal of the Standard

The goal of the air quality performance standard is to minimize the effects on people’s health and the environment from air emissions during the cleanup. Since PCBs are the primary pollutant in the sediment the performance standard, displayed at right, sets the limits for PCBs in the air.

How the Standard Works

  • Regular monitoring at multiple locations
  • Taking action to minimize air quality effects
  • Reporting and notification by the cleanup team to EPA

 

View Phase 1 Monitoring