Phase 1 Far-Field Water Quality Monitoring (Resuspension)
Phase 1 Weekly Calendar (Please click on data for more information)
Phase 1 dredging occurred between May 15 - Oct 26, 2009. Performance standard monitoring data was collected daily between
May-Dec 2009. Once all Phase 1 river activities were completed, and baseline (pre-dredging) water PCB levels were reached,
weekly monitoring began (December 28, 2009). Baseline monitoring results are received in accordance with standard lab turnaround
time (approx. 21 days).
Phase 1 Calendar
| Rogers Island | Thompson Island | Thompson Island (additional results) | Schuylerville (Lock 5) | Schuylerville (Lock 5) (additional results) | Stillwater | Waterford | Albany | Poughkeepsie | |
|---|---|---|---|---|---|---|---|---|---|
| Apr 24 | - | - | - | - | - | - | - | - | - |
| Apr 25 | - | 31 | - | 18 | - | - | 12 | - | - |
| Apr 26 | - | - | - | - | - | - | - | - | - |
| Apr 27 | - | - | - | - | - | - | - | - | - |
| Apr 28 | - | - | - | - | - | - | - | - | - |
| Apr 29 | - | - | - | - | - | - | - | - | - |
| Apr 30 | - | - | - | - | - | - | - | - | - |
Phase 1 Dredging Monitoring Schedule
Routine Monitoring is performed during typical operations, and Contingency Monitoring is performed when the Control
Levels are exceeded.
| Sampling Frequency | Rogers Island | Thompson Island | Schuylerville (Lock 5) | Stillwater | Waterford | Albany | Poughkeepsie |
|---|---|---|---|---|---|---|---|
| Routine | Weekly | Daily | Daily | Weekly | Daily | Monthly | Monthly |
| Contingency | Daily | Twice Daily | Twice Daily | - | - | Weekly | Weekly |
Phase 1 Baseline Monitoring Schedule
| Sampling Frequency | Rogers Island | Thompson Island | Schuylerville (Lock 5) | Stillwater | Waterford | Albany | Poughkeepsie |
|---|---|---|---|---|---|---|---|
| Baseline | Monthly | Weekly | Weekly | - | Weekly | Monthly | Monthly |
Engineering Performance Standards: Resuspension
Strict Engineering Performance Standards have been developed to minimize resuspension of PCBs during dredging to limit the transport of PCBs and protect water intakes.
What is the Phase 1 Standard?
The performance standard for dredging resuspension sets a resuspension level of 500 parts per trillion (ppt) Total PCBs – the EPA drinking water standard under the Safe Drinking Water Act.
How is the Phase 1 Standard Measured?
Through an extensive river water quality monitoring program at upstream, “near-field” and “far-field” stations.
near-field: within 300 meters downstream of dredge (turbidity, total suspended solids and metals)far-field: greater than 1 mile downstream (total suspended solids, metals and PCBs)
(see Far Field Water Monitoring Locations map at left)